Experience

SUNGDO ENG (CPIP

SEMPHIL P4 PJT UTILITY BLDG & ANCILLARY FACILITIES

January 2016 - February 2017

  • Mechanical Piping Works
  • Underground Piping Works
  • Pipe Rack Structures Piping
  • Chilled Water Installation & Piping
  • HVAC Fabrication & Installation

SUNGJIN ENGINEERING (CPIP

SCRUBBER INSTALLATION & PIPING WORK (SEMPHIL)

April 2017 - July 2017

  • Installation of  6 units scrubber
  • Structure Installation
  • Piping works
  • Painting works

SUNGDO ENG (CPIP 

SEMPHIL P4 PJT UTILITY BLDG & ANCILLARY FACILITIES

January 2016 - February 2017

  •  Welfare and Utility 1 & 2 area Electrical wire installation

SUNGJIN ENGINEERING (CPIP

SCRUBBER INSTALLATION & PIPING WORK (SEMPHIL)

April 2017 - July 2017

  • Installation of  6 units scrubber
  • Panel Board Installation & Wiring
  • Cable Pulling & Cable tray wire installation

SUNGDO ENG (CPIP

SEMPHIL P4 PJT UTILITY BLDG & ANCILLARY FACILITIES

January 2016 - February 2017

  • HVAC Fabrication & Installation at Utility 1 & 2 Area & Welfare Area
  • Aluminum & Rubber Cladding Works

Joong ang ar. co. (LAs pinas

CYCLOTRON CENTER OF PERPETUAL HELP MEDICAL CENTER

February 2015 - March 2015

  • HVAC Installation at Cyclotron Center
  • Aluminum & Rubber Cladding Works

SUNGDO ENG (CPIP

SEMPHIL P4 PJT UTILITY BLDG & ANCILLARY FACILITIES

January 2016 - February 2017

  • Pipe & Sprinkler Head Installation at Utility 1 & 2 area, warehouse area, & welfare area

SUNGDO ENG (CPIP

SEMPHIL P4 PJT UTILITY BLDG & ANCILLARY FACILITIES

January 2016 - February 2017

  • Installation of various pipe line such as water line, sewer line, chilled water line, storm drainage and fixture unit at P-4, utility 1 & 2 area, warehouse, welfare area and scrap building area.

Joong ang ar. co. (LAs pinas

CYCLOTRON CENTER OF PERPETUAL HELP MEDICAL CENTER

January 2016 - February 2017

Hospital equipment setting and installation for cyclotron center

SUNGDO ENG (CPIP

SEMPHIL P4 PJT UTILITY BLDG & ANCILLARY FACILITIES

January 2016 - February 2017

  • Mechanical Piping Works
  • Underground Piping Works
  • Pipe Rack Structures Piping
  • Chilled Water Installation & Piping
  • HVAC Fabrication & Installation

EN TECH (LAGUNA 

SEMPHIL WWT SLEEVE INSTALLATION & PIPING

May 2016 - July 2016

  • Fabrication & Installation for utility 1 & 2 piping works

SUNGJIN ENGINEERING (CPIP

SCRUBBER INSTALLATION & PIPING WORK (SEMPHIL)

April 2017 - July 2017

  • Installation of  6 units scrubber
  • Structure Installation
  • Piping works
  • Painting works

SUNGDO ENG (CPIP

SEMPHIL P4 PJT UTILITY BLDG & ANCILLARY FACILITIES

January 2016 - February 2017

  • Utility Piping works
  • Manpower Supply